110 engineering problems
This is the season’s engineering register: 110 numbered problems, each with the requirement that creates it, the experiment that produces the missing number, and the criterion that closes it. Every problem traces to at least one 2027 requirement, and all 155 requirements are covered by at least one row. The rows are ordered by dependency wave rather than by subsystem, because the order in which the work becomes possible is not the order in which subsystems are usually written down.
Key takeaways
- The first four things to do are measurements, and none of them resembles a design-review deliverable. The numbers that size the rover are unpublished, and the season is won by replacing them before the design is committed.
- Thirteen rows have five or more dependents. They are the spine of the season, and only they should be scheduled without an argument.
- The arm decision silently consumes the drivetrain margin. An arm in the 14 kg class lands the rover 0.3 kg below the mass at which the chosen actuator class stops being adequate, and the next bracket costs 2.7 kg for six larger actuators.
- The SAR forces a February evidence programme. The submission is due ten days before the test wave opens, so four missions have to be filmed at partial fidelity while the rover is still being integrated.
What a row contains
| Field | What it gives | Why it exists |
|---|---|---|
| ID | A stable identifier for the life of the project | The risk register, the reviews and the team tracker all reference it |
| Problem | One testable sentence with no solution inside it | A problem that contains its answer is a decision already taken |
| First experiment | The smallest thing that produces the missing information, sized in days | If it needs the whole rover, it belongs in a later wave |
| Success criterion | A number or a binary, written before the experiment runs | Rule numbers are quoted; a design target is labelled as derived |
| Unlocks | How many later problems depend on this one | The working measure of downstream design unlocked |
| Traces to | The requirement and the rule or ruling behind it | Every problem exists because the 2027 rules require something |
Priority is deliberately coarse. 29 rows are Critical: open at their gate, with the season at risk through a pass-or-fail rule, a milestone, or a measurement that three waves depend on. 72 are High: they block three or more later problems or a whole mission capability. 8 are Medium and 1 is Low, recoverable later without a rule breach.
The fine ordering is the unlock count, and the two are meant to be read together. A High row with eight dependents is better value than a Critical row with none, which is the case for a May submission deadline.
The five waves
| Wave | Problems | Weeks | Calendar | What it is for | Gate |
|---|---|---|---|---|---|
| W0 Measure | 23 | 0–4 | 2026-10-26 to 11-22 | Bench, rig and field measurements that replace the rulebook’s missing numbers; the judge-like task mock | none |
| W1 Architecture | 26 | 4–12 | 2026-11-23 to 2027-01-17 | The irreversible or expensive-to-reverse choices, each with a freeze date | PDR 2026-12-02, week 5 |
| W2 Detailed design | 28 | 12–20 | 2027-01-18 to 03-14 | Interface documents, sizing analyses, procedures and the February evidence runs | SAR 2027-03-05, week 19 |
| W3 Integration and test | 20 | 20–27 | 2027-03-15 to 05-02 | The rover assembled and the four missions run against a clock | test evidence for the finals |
| W4 Review and rehearsal | 13 | 27–31 | 2027-05-03 to 06-01 | Review responses, frozen procedures, rehearsal and the final documents | Science Plan 2027-05-21, finals 2027-06-02 to 06-05 |
The five waves sum to 110. The PDR is due 2026-12-02 S-URC27-RULES §3.a.ii, the SAR 2027-03-05 S-URC27-RULES §3.a.iii, and the finals run 2027-06-02 to 06-05 S-URC27-RULES §3.a.iv. The communications documentation is due 2027-04-30, in the last week of W3, so its substance has to be finished before that week opens.
All 110 problems
The table is searchable and sortable, and it filters by wave and by priority. Dependency counts are in the Unlocks column; a row with a high count is a row that frees design work elsewhere.
The dependency spine
110 problems connect through 253 dependency edges. Thirteen rows have no prerequisite, because they are pure measurements, and twenty-one are leaves, because they are submissions, rehearsals or drills. Thirteen rows carry five or more dependents, and they are the rows that decide when the rest becomes possible.
| Rank | ID | Problem | Priority | Unlocks | Why it is load-bearing |
|---|---|---|---|---|---|
| 1 | W0-01 | Mass budget frame, weigh-in procedure and the 1.2 m gauge | Critical | 9 | Feeds the arm class, wheel size, stow concept, configuration plan and weigh-in |
| 2 | W0-11 | Link budget model and the first 1 km non-line-of-sight test | Critical | 8 | Decides radios, bands, camera count, mast, drone value and the licence package |
| 3 | W0-14 | Real tag and sign detection ranges in full sun | High | 8 | Sets every camera and lens, the arrival strategy and the gesture range |
| 4 | W0-09 | Wheel and soil traction, and rolling resistance | High | 7 | The physical basis of torque, slope limit and route planning |
| 5 | W1-01 | Rover mass class, arm mass class and the actuator cliff | Critical | 7 | The arm class quietly chooses the drivetrain actuator class |
| 6 | W1-03 | Wheel diameter, wheelbase, track and stow geometry | Critical | 7 | The least reversible number in the project |
| 7 | W0-02 | A judge-like Equipment Servicing mock | Critical | 6 | Makes every task-force measurement possible |
| 8 | W1-15 | Compute and camera architecture against the link budget | High | 6 | Sets link load, thermal load and the software target |
| 9 | W1-19 | Modularity and configuration plan | High | 6 | The 70 kg rule, the 10-minute transition and the operator roster in one decision |
| 10 | W2-23 | Operations procedures, first version | High | 6 | Turns a test programme into repeatable evidence |
| 11 | W0-03 | Task force and torque measurement campaign | Critical | 5 | Sizes the arm, the gripper and the compliance |
| 12 | W0-07 | Soil and drilling force measurement | Critical | 5 | Decides the sampling architecture and the chassis reaction path |
| 13 | W0-10 | Step and obstacle rig, climb against wheel diameter | Critical | 5 | Sets the wheel diameter, the torque demand and the tilt limit |
Six of the thirteen rows are in the measurement wave. That is the register’s central claim about a first build: the numbers that size the machine are not published, so the early season is spent producing them.
Working the register every week
A register that is read once is a document. One that is reviewed weekly is a management system, and the minimum useful ritual is 45 minutes, five questions, in this order.
- What closed this week, and what artefact proves it? A row closes only when its success criterion is met and the record is filed where the SAR evidence can be found. A measurement either exists or the row is still open.
- What is now unblocked? Every closed row carries the number of later problems it unlocks. Those are the candidates for next week, and they are the only rows that should be scheduled without an argument.
- Which Critical row is nearest its gate? The PDR gate set and the SAR gate set are fixed, so anything in them that cannot close in the remaining weeks is a scope decision to take now.
- What did a measurement contradict? A number that disagrees with a subsystem study is a finding: record it in the row and in the study, and re-run the rows that used the old number.
- Which question now blocks more than one row? If a written question has grown dependents, escalate the email rather than guessing in two places.
A worked row
The wheel-diameter row, W1-03, shows what a well-formed entry looks like. The problem is stated as a decision rather than a preference: fix wheel diameter, wheelbase and track. It depends on four measurements: the mass frame (W0-01), traction (W0-09), the step rig (W0-10) and the arm mass class (W1-01). Its first experiment is a packaging study of 250, 280 and 330 mm wheels inside the cube gauge, plus a tip-angle calculation at each diameter. Its success criterion is a diameter that fits the cube with 20 mm per side, keeps the static tip angle at or above 55° as a derived target, and has a bearing and shaft design at the measured torque. The artefact is a signed envelope drawing, the packaging calculation and a photograph in the gauge. It unlocks seven rows: gear ratio, suspension, mast height, chassis, the mass and centre-of-gravity document, kinematics, and the structural load cases.
That shape is the test for every row: a decision, its inputs, one experiment, one number, one artefact, and the list of what it frees. A row with no number in its success criterion is a topic, not a task.
Coverage of the 155 requirements
Every one of the 155 requirements is traced by at least one problem: 155 cited, zero uncovered, zero unknown identifiers. The distribution is itself a check on the analysis.
| Domain | Requirements | Covered by a row |
|---|---|---|
| Arm | 21 | 21 |
| Science | 20 | 20 |
| Software | 19 | 19 |
| Communications | 15 | 15 |
| Compute and perception | 15 | 15 |
| Systems | 14 | 14 |
| Operations | 12 | 12 |
| Mobility | 11 | 11 |
| Delivery and drones | 11 | 11 |
| Power | 9 | 9 |
| Safety | 8 | 8 |
| Total | 155 | 155 |
The drone is the thinnest area, at eleven requirements carried by four problems and one of them Low priority, which matches the absence of any strong drone evidence in the record. Safety has eight requirements and eight problems, three of which are tests, the right ratio for a pass-or-fail clause.
Twenty-one requirements are carried by exactly one row, and twelve of those are mandatory. Two are worth watching, because a single scheduled item is load-bearing for something scored. The panorama and close-up requirements, REQ-SCI-007 and REQ-SCI-008, both rest on the Astrobiology rehearsal W3-08, so a documentation-only dry run is added earlier. REQ-SAF-004, that every mobile deployable carries its own E-stop, rests on W2-24 and is correct only while nothing is deployed.
Twenty questions the register gates
Twenty questions in the register are the ones no amount of engineering can settle. Each is a written question to the URC Director, each gates named rows, each has an answer date, and each has a conservative fallback so that an unanswered question never stops work. The four with the largest design consequences are below; the open questions page carries the wider set of 77.
| Question | What it decides | Ask by | Fallback if unanswered |
|---|---|---|---|
| Does one instrument with two readouts count as two life-detection capabilities? | Payload architecture and the SAR science page | 2026-11-15 | Build two independent channels on one detector |
| Do the antenna height and base-distance limits apply to a separate GNSS base antenna? | The RTK geometry and the 1 m stop | 2026-11-15 | Apply 3 m and 5 m to all base antennas |
| Must a spare drone battery carried but not connected sit inside the E-stop rule, and does it count in 70 kg? | Battery architecture, the drone plan and the weigh-in | 2026-12-01 | Carry no spare drone battery on the rover |
| What provenance record must accompany the cache? | The cache design and the hand-over procedure | 2026-12-01 | Print a provenance card, seal it and photograph it in place |
Each question goes as one numbered email that quotes the clause, states the interpretation the team intends, and asks for confirmation or correction, with a request that the answer be mirrored onto the public Q&A page, which is itself a binding rule source. The reply is recorded against the rows it gates.
What would make this register wrong
- The 2027 numbers move. The 50 kg, 70 kg and 1.2 m limits, the five milestone dates and the mission structure are confirmed for 2027. A rules revision would force every row that cites the mass, the timeline or the mission structure to be re-read before the next review.
- A task weight changes the order, not the content. The Astrobiology, Delivery and Equipment Servicing weights are unpublished. When they arrive, the sequence inside the last two waves changes, because the highest-points task is attacked first; the problems themselves do not.
- A measurement can overrule a study. Every value carried over from a subsystem study is an estimate until the measuring row closes. Where a measurement disagrees, the measurement wins and the row records the difference.
- The plan assumes one rover. Two mission configurations with a real payload change would grow W1-19 and W2-05 and turn the 10-minute transition into a rehearsal item with its own test.
Further reading
- 70 risks points every risk at a problem row, so a risk with no row is a missing row here.
- 77 open questions carries the full question set and the meanwhile assumption for each.
- The first 90 days reads these dependencies forwards, week by week.
- 155 engineering requirements is the table every row traces into.
- Coupling, conflicts and twelve trade studies settles the design decisions the architecture wave tests.
- Interfaces and couplings supplies the interface rows the detailed-design documents must contain.
Sources for this page
- S-URC27-RULESUniversity Rover Challenge 2027 – Requirements and GuidelinesOriginal Archived copy